Safely Managing Nuclear Remediation Projects
Even the best cost estimators and project managers can rarely capture all of the time and effort truly needed to support a fast-paced project.
- By Jeff Bowers
- Apr 15, 2008
For the better part of 30 years, I have
been involved in a variety of nuclearrelated
projects. This is what I know:
For the most part, if you give the craft
accurate drawings, the tools they need to
perform their work, and clear direction,
they will perform for you every time. If
your staff has a well-defined scope, open
communication, and management support,
they will perform, as well. If you are doing
all of these things and still find project success
elusive, what’s missing? I have found
that management credibility in regard to
safety is the key.
Lessons Learned
It’s crunch time as the final days before
proposal submittal draw near. A concentrated
effort to focus attention on the RFP,
amendments, drawings, and specifications
demands intense focus. Having performed
these tasks a hundred times, the staff homes
in on the fine-tuning of each line item,
reevaluating identified risk, stakeholder
issues, lessons learned, subcontractor cost,
the all-important margin, and contingency.
Unfortunately, accounting for the time,
material, and equipment to support a safe
radiological project usually means your bid
will be too high. Faced with the dilemma,
some firms struggle with inclusion of cost
and resources necessary to fully capture
the safety element. After award, in all too
many cases, the task of managing a project
safety is placed squarely on the shoulders
of project managers. Profitability, after all,
is the bottom line for advancement, company
reputation, positioning for future
work, and a powerful company reference
for proposals.
Quite frankly, being safe is expensive
and never fully accounted for in building a
standard Work Breakdown Structure (a
deliverable-oriented, hierarchical decomposition
of the work to be executed by the
project team to accomplish the project
objectives). What I mean with this statement
is the cost of safety equipment; the
time devoted to safety reviews, meetings,
and briefings is expensive. The responsibility
for the project manager is the timehonored
art of balancing safety and production
and relaying that approach to the
field staff; this, and being believable. I’ve
learned to favor safety every time. This
approach has served me well for decades.
Once you add the nuclear component
to the safety mix, even the best cost estimators
and project managers can rarely capture
all of the time and effort truly needed
to support a fast-paced nuclear remediation
project. However, given even the tightest
budgets, a project manager can gain respect
and credibility by conveying an absolute
insistence for safety. Craft in particular can
instinctively sense management’s approach
and commitment to safety and can tell
whether the radiological aspects are understood
by their supervision.
Even with the best intentions, radiological
training for staff and craft are at best a
measure of who can comprehend the rules
and guidelines well enough to pass an
exam. So back to safety and setting proper
examples: It doesn’t matter whether the
project spans several months or several
years and employs 10 or 1,000
employees—safety credibility is the key.
Taking appropriate time up front to
address the contractually stated scope in
regard to working in a radiological environment
will be the single most valuable
time a project manager can invest.
Typical environmental restoration
projects can range from $500,000 to $500
million and more. Many sites require
everything from initial site characterization
through final status surveys. Most of
these projects include the initial determination
and relocation of existing utilities,
alarm systems, and vital security hardware.
The primary hazards are confined
spaces, fall protection, lead and asbestos
abatement, and toxic material remediation.
This work entails complex demolition
scope and innovative design and
engineering activities.
Unforeseen and changing site conditions
are as much of the project dynamic as
the stated scope. Addressing these issues,
and more importantly, relaying their
impact to the project workforce is an
increasingly imperative project management
attribute.
A complete understanding of radiological
contamination levels and exposure
controls is critical to preparing pre-construction-
phase activities training. In
regard to the Project Readiness Assessment,
it’s essential to include the health
physics discipline in the preparation of
these processes.
Never underestimate the power of
credibility in respect to achieving project
objectives. From this PM’s perspective,
being credible and setting examples from
the outset is vital to leading a successful,
safe project. After that, instituting a credible
management approach to radiological
safety is an absolute key.
This article originally appeared in the April 2008 issue of Occupational Health & Safety.